Week of 04-24-23
- Begin Monday 04-24-23
- Tuesday 04-25-23, lane closure on Pilot Knob for pavement and curb removals
- Roadway grading and common excavation
Week of 05-01-23
- Continue roadway grading and aggregate installation
Week of 05-07-23
Concrete installation Wednesday 05-10-23
Contact Tim Biberdorf with questions at 952-953-2427 or Tim.Biberdorf@applevalleymn.gov .