Week of 04-24-23

  • Begin Monday 04-24-23
  • Tuesday 04-25-23, lane closure on Pilot Knob for pavement and curb removals
  • Roadway grading and common excavation

 Week of 05-01-23

  • Continue roadway grading and aggregate installation 

 Week of 05-07-23

Concrete installation Wednesday 05-10-23